Project in hospital

Since the emergency room of the hospital needs to operate 24 hours a day, the front section of the main pipe of the 200mm cold water air-conditioning system has been connected to the air-cooling cabinet to supply air conditioning to the emergency room. The rear section needs to be re-piped for the cold water air-conditioning system! Because the cold water air conditioning system was in operation, the traditional "ice throat" solution could not be implemented, so we finally contacted the engineer.